Solar farm / Under development
Tönnersjö
Halmstad – Sweden
Est. 400 MWp
Total power
Max. 450 Ha
Area size
Est. 2033
To be operational
Ilmatar is planning a 450-hectare solar park in Tönnersjö, at Halmstad Tönnersjöheden 23:4 in Halmstad municipality. For this purpose, the applicant has signed a lease agreement with the property owners. The area mainly consists of production forest ready for harvesting and is estimated to have limited natural values.
Ilmatar conducted a delimitation consultation in March 2023. The application for an environmental permit was submitted to the County Administrative Board of Halland on 30 April 2024.