Ilmatar Energy Oy’s subsidiary, Ilmatar Seinäjoki Oy, is planning a wind farm in the eastern part of the city of Seinäjoki, near the border of the municipality of Kuortane.
Back to projects
Onshore wind / Under development
Palopättäränmäki
Seinäjoki – Finland
Est. 105 MW
Total power
Max. 14
Number of turbines
Max. 225 / 350 M
Hub height / Tip height
Est. 2029
To be operational
The project includes up to 14 wind turbines with a total nominal capacity of approximately 105 megawatts (MW).
The environmental impact assessment (EIA) procedure for the project was completed in 2024. The draft zoning plan was displayed for public review from 7 December 2023 to 2 February 2024. After this, the preparation of the proposed zoning plan has begun, with the aim of submitting it for approval during 2026.
The construction phase is expected to take place in 2028–2029, allowing electricity production in the area to begin in 2029 at the earliest.
Project location
Contact
Contact me if you need more information about this project.
News & Views
Projects
Related projects
Our core business is dedicated to solving one of Earth’s most crucial and complex challenges, climate change.