Back to projects
Onshore wind / Under development

Hukkalansalo

Paltamo – Finland
Hukkalansalo
Est. 142.5 MW Total power
Max. 19 Number of turbines
Max. 200 / 310 M Hub height / Tip height
Est. 2030 To be operational

Ilmatar is planning a wind farm of 19 turbines in the northern part of Paltamo. The Hukkalansalo planning area is located between the villages of Vaarankylä, Saarinen, and Raappananmäki, on an uninhabited area primarily used for forestry. In the updated regional wind power plan for Kainuu, the Hukkalansalo area has also been designated as a regionally significant area for wind power development.

The zoning process for the project began in autumn 2021, and the Centre for Economic Development, Transport and the Environment (ELY Centre) issued a reasoned conclusion on the project’s Environmental Impact Assessment (EIA) procedure in February 2024. Following this, Ilmatar abandoned two turbine locations previously planned on the Puolanka side (Julkuvaara), and the maximum height of the turbines was reduced from 350 metres to 310 metres to minimize visual impacts. Turbine locations were also refined to take into account valuable natural sites and cultural heritage identified during the EIA process.

The draft plan was available for public viewing from March 4 to April 3, 2025, and an open public event on the zoning process was held on March 13, 2025, at Paltamo Town Hall. Based on feedback received during the proposal stage, additional nature surveys were conducted in the area in spring 2025. As a result of these surveys, the locations of some turbines were adjusted to better safeguard natural values. On December 15, 2026, the Paltamo municipal board decided in its meeting to make the draft plan available for public viewing again from January 2 to February 2, 2026. The approval of the partial master plan is scheduled for spring 2026.

The construction schedule of the wind farm depends on the renovation timetable of Fingrid’s Nuojuankangas–Seitenoikea power line. A new 400+110 kV transmission line will be built alongside the existing 220 kV line north of Hukkalansalo, to which the Hukkalansalo wind farm will be connected.

Project location

Timeline and Key Phases of the Hukkalansalo Project

2020

Ilmatar identifies the Hukkalansalo area as suitable for wind power in its preliminary studies and initiates land lease negotiations.

2021

The Defense Forces give a favorable statement for the project. The municipality of Paltamo approves Ilmatar’s zoning initiative.

2022

Comprehensive environmental studies are conducted in the area, and the project’s EIA program and the zoning participation and assessment plan (OAS) are made available for public viewing.

2023

The project’s EIA report and the draft partial master plan are made available for public viewing.

2024

The Kainuu Regional Council approves the Wind Power Regional Plan 2035 and orders it to come into force. The Hukkalansalo area is designated as a regionally significant area for wind turbines in the regional plan. The Kainuu ELY Center provides a reasoned conclusion on the EIA procedure. The draft plan is prepared, taking into account the conclusions of the EIA procedure to reduce environmental impacts.

2026

Approval of the plan.

2026-2027

Technical design of the wind farm and arrangement of project financing.

2028

Investment decision for the wind farm and start of construction.

2030

The wind farm begins electricity production.

Contact

Contact me if you need more information about this project.

Jussi Mäkinen

VP, Project Development

jussi.makinen@ilmatar.com