Back to projects
Onshore wind / Under development

Lylyharju

Kihniö/Parkano – Finland
Lylyharju
Est. 105 MW Total power
Max. 14 Number of turbines
Max. 175 / 290 M Hub height / Tip height
Est. 2029 To be operational

Ilmatar is developing a wind power project in the Lylyharju area, located at the border of the municipalities of Parkano, Kihniö, and Kurikka. The area has the potential to accommodate a maximum of 14 wind turbines.

Current Situation

The schedules for the local master plans of the three municipalities involved in the Lylyharju wind power project have been decided to proceed separately. In Parkano, the local master plan for three wind turbines was approved in spring 2025. In Kihniö, the proposal for six turbines is planned to be made available for public review in spring 2026, with the goal of approval later that year. In Kurikka, the conditions for preparing a plan proposal are currently being assessed.

Extensive studies have been carried out in the project area, which have helped refine the turbine locations. According to these studies, the area is very suitable for wind power production. Lylyharju has also been identified in the Pirkanmaa Regional Plan for Biodiversity and Energy, approved in 2025, as a suitable area for wind power.

Project location

Timeline and Key Phases of the Hukkalansalo Project

2019–2020

The Lylyharju area was identified in preliminary studies as suitable for wind power. Negotiations for land lease agreements with local landowners began.

2021

2021 – The zoning initiative was approved in all three municipalities, and the project’s EIA program and the participation and assessment plan (OAS) were made available for public review.

2023

The project’s EIA report and the draft local master plan were made available for public consultation.

2024

The zoning proposal for Parkano was made available for public review, and wind measurements were initiated in the area.

2025

The Parkano local master plan was approved.

2026

The zoning proposal for Kihniö will be made available for public review, with the approval process to follow.

2027

Detailed technical planning of the wind farm.

2028

Investment decision for the wind farm and start of construction.

2029

The wind farm begins electricity production.

Contact

Contact me if you need more information about this project.

Marko Penttilä

Project Development Manager

Ilmatar

+358 40 565 4151 marko.penttila@ilmatar.com